Match Capacity with the Scope of the
Project
Successful housing development requires rigorous planning and clear definition
of roles and responsibilities among the members of the Development and Construction
Team. The Project Management Section addresses how to assemble and manage the
overall Project Development Team while this section focuses on the Construction
Team, which has direct responsibility for building and/or rehabilitating the
house(s) on time and on budget.
The following are key issues that the developer must resolve in assembling
an effective Construction Management Team:
|
What
is the scale of your project? What type of talent, capacity, skills
and experience is needed to supplement what you organization has to offer?
Clarify
construction quality standards and/or code issues of your organization,
the municipality, lenders and funders. Distinguish bottom line standards
in terms of code compliance, marketability of the house product, and values
of your organization (e.g. brick versus siding).
Know
thyself! Staff and Board members need to assess what is their capacity
to manage the complexities of the construction management process. What
are you good at? What do you like to do and what do you want to get better
at?
You
are responsible for setting the tone and norms for communication,
decision-making and accountability to keep the process moving.
Take
the initiative to find quality talent and be prepared to pay accordingly.
You get what you pay for. If it is too good to be true, it usually is.
|

Levels of Construction
The scale of construction impacts how to organize your construction team.
The following are the most common levels of construction in homeownership development:
|
1. Moderate Rehabilitation of Existing Houses
Moderate rehabilitation is needed when the major systems, such as the electrical,
plumbing, heating, and roof are in working order and meet code standards.
However, some level of improvements for both function and appearance is
needed. Moderate rehabilitation may involve the replacement of no more than
one or two major building systems and upgrades of baths and kitchens and
cosmetic renovations.
2. Substantial Rehabilitation Of Existing Housing
Substantial rehabilitation can involve:
|
|
Repair
and/or often complete replacement of all major building systems
Removal
of any and all hazardous materials (no encapsulation)
Repairs
to the building structure
Possibly
re-design of floor plans and room additions |
|
Substantial rehabilitation often requires engaging the services
of an architect and engineer in order to provide working drawings and detailed
specifications of what and how to rehabilitate the house. Moderate rehabilitation
can often be directed by simply using a detailed Scope of Work.
People often think of Substantial Rehabilitation in terms of the most
derelict, blighted, unstable properties. Questions often asked are "Why
bother to rehab? Why not tear down and re-build?" It is often more cost-effective
to demolish and re-build houses that have totally deteriorated roofs,
plumbing, electrical, HVAC and structural systems. If the property is
detached and there is enough land on the lot, introduction of a modular
house could be a very cost-effective alternative. However, if the house
is in the middle of a row of houses or is one half of a semi-detached
house, then there is a stronger case to explore the cost-benefits of rehabilitation.
Many nonprofit Boards of Directors instruct staff to rehabilitate as
much as possible in order to preserve the look and character of the neighborhood
housing stock. Often these sensibilities are impacted by a desire for
historic preservation of properties. Historic preservation is very costly
and often not the most affordable housing option for the low-income buyer.
Therefore CDCs that seek to initiate historic rehabilitation programs
should make sure that their source of funding allows for higher per unit
development costs and opportunities for moderate-income families (who
have more money for maintenance) to purchase.
3. New Construction
New Construction is chosen when there is a vacant piece of land on which
to build several units, when there are individual vacant lots ("in-fill"
housing), and when there are dilapidated units that will be demolished.
Today, with all of the exterior design options available, it is possible
to build a new unit with finishes that make the house fit right into an
existing neighborhood. New construction is often chosen to save costs.
There may be substantial economy of scale when a number of housing units
are under contract with one contractor. In addition, there are two ways
to build new - "stick-built" units, that are constructed from the ground
up, and modular units because they can be built and delivered within 6-8
weeks and assembled on-site in less than a month - which allows a new
house to be built and sold in less than 3 months.
|
Modular Construction - Pros and Cons
| |
Pros
Impact
is immediate because of the speed of construction
Less
material theft; increased security, as property is enclosed almost from
the start
More
predictable costs; smaller construction contingency
Standardized
construction quality
Fewer
subcontractors
Slightly
less affected by weather / construction season
Cons
Less
flexibility in design, particularly for narrow urban lots.
Not
less expensive to develop
Negative
public perception - that they are trailers
TIP
Be sure you are clear on what the modular builder is providing.
Who is responsible for site work such as basements/foundations, walkways,
sewer and water taps, plumbing hookups, electrical hook-ups and permitting
for those services.
Who is responsible for delivery, police escorts, if necessary, street
closure permits, crane and heavy equipment permits, etc.
Who is responsible for porches, garages, gutters, downspouts, rough grades
around the house, finish grades around the house.
|
Construction Team Roles
As Project Manager, the developer is responsible for getting the houses built and delivered to the buyers. This involves many skilled professionals:
Construction Manager - The construction manager coordinates all phases
of the construction project and acts as a liaison between all parties. The duties
of the Construction Manager are:
Pre-Construction:
|
coordinates
with all project professionals on all issues related to design
establishes lines of communication with all inspectors and inspection agencies
procures
all owner-related testing and reports, including soil test reports and Phase
I environmental
coordinates the bidding process and selects the General Contractor
negotiates the final pricing and prepares the construction contract for approval |
During Construction:
|
holds reconstruction meetings
coordinates construction site meetings with the general contractor and architect
reviews requests for payment and conducts inspections prior to payment
reviews all change order requests
reviews all shop drawing
inspects work in place |
Project Close Out:
|
coordinates
the punch list preparation and follow-up inspections
requests warranty information from the general contractor
readies the completed unit for the new buyer |
Architect - The architect's responsibilities vary from just providing
preliminary feasibility analysis to full design and construction oversight when
needed. Typically, the architect coordinates the design process and involves
other design professionals as needed.
Civil Engineer - The civil engineer, also known as the site engineer,
deals with such issues as zoning approval, roadway design and large scale landscaping.
This responsibility revolves around the design of the entire project, such as
parking lot layout and development perimeters. The civil engineer is the key
professional involved in the planning and zoning processes. This person is responsible
for surveying the site and locating all existing and proposed structures on
a drawing that can be presented to the municipality. The civil engineer is responsible
for determining the need for any zoning variances or changes that may be required.
Landscape Architect - Once the development perimeter has been established
and the site design has been set, the landscape architect determines which plantings
are appropriate for the site and addresses such concerns as erosion control,
wetland issues and the finished "look" of the project. Using landscape architects
allows the developer to plant trees and shrubs that look appropriate to the
project and can withstand the climate. The architect chosen should be sensitive
to the upkeep requirements of the plantings in the affordable housing units.
Environmental Engineer - The environmental engineer is usually the
first professional consulted on the development project and performs the crucial
Phase I environmental site assessment.
Mechanical Engineer - The mechanical engineer is responsible for the HVAC system, plumbing and piping design and the design of the sprinkler system, if needed.
Electrical Engineer - The electrical engineer is responsible for all issues related to electricity traveling through wires around any structure. This includes the general power system into each house as well as the electrical set-up inside.
Historic Preservation Consultant - The historic consultant is hired
to deal with local officials, such as the National Park Service and historical
societies, for houses and structures that are on the historic register, to ensure
that the renovation is consistent with historic preservation guidelines.